Estimated Title Date: July 2025
Scheduled
In Progress
Complete
Earthworks
The topsoil is removed and stored for later use. The land is shaped to lot designs and for drainage to Melbourne Water standards.
Complete
Sewers
All trunk and reticulation sewers are constructed, providing sanitation services to each house lot.
Complete
Stormwater Drainage
Stormwater pipes and pits are constructed to drain stormwater away from house lots and prevent flooding. Works may also include basins and wetlands to treat stormwater before it enters local waterways.
Complete
Water & Gas
Pipes to carry water, recycled water and gas to each house lot, all trunk and reticulation services, are constructed.
Complete
Retaining Walls
Where required, retaining walls are constructed to manage surface level changes and provide suitable lots for house construction.
Complete
Road Boxing & Base
Roads are boxed out and service crossings are installed. Strong road bases are built by densely compacting layers of crushed rock.
Complete
Road Kerb & Channel
Concrete kerbs are installed along the edges of the new roads to help transfer stormwater runoff into the drainage network.
Complete
Power & Telecommunications
Power, internet and phone services are installed, ready for connection to each home. Street lighting is also installed.
Complete
Asphalt
The final step in road construction is laying asphalt, to provide a smooth driving surface for vehicles.
Complete
Statement of Compliance & Testing
All work to date is tested and audited by the relevant service authorities. Once approved, the stage receives a Statement of Compliance from Council verifying that the stage is ready to lodge for individual lot titles.
Complete
Lodgement at the Titles Office
The stage is lodged with the Titles Office to create individual titles for each lot. When titles are granted settlement can take place.
Complete